top of page

COASTAL

Coastal Works carried out by Arun District Council on the Middleton on Sea sea defences and foreshore.

Listed below is the coastal works carried out Arun District Council. MOSA would like to acknowledge the support and help given to us by ADC and Cllr. Barbara Oakley, who over the years have protected our defences and foreshore. Also for involving us and keeping us updated.

 

2019

Groyne 155, adjacent to Old Point, was been subjected to heavy loading resulting in the driven members separating from the structure. Emergency repairs were carried out in order to underpin the groyne.

 

2018

A phase of enhanced repair and maintenance was carried out installing 12m³ of tropical hardwood. The works were completed in order to remove the softwood counterparts that had begun to fail. Ad-hoc sea-wall repairs were also carried out including the reinstatement of the fatiguing expansion joints.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2017

General repair and maintenance including filling, placing and covering of geotextile shingle containers. The geotextile containers have been used as an alternative to gabion baskets which have been observed as leaving sharp debris when failing.

 

2016

General repairs and maintenance to the timber groyne field adjacent to Sea Way. A repair was carried out to a small portion of the Old Point seawall cover slab to eliminate the possibility of an increase in lateral earth pressure.

 

2015

Following successive storm action the metal piles that retain the head of groyne 155 broke free. The piles were re-seated and the groyne rebuilt accordingly.

 

2014

Extensive softwood repairs to the timber groynes and breastwork. The wall that retains the access steps to Old Point failed requiring Arun District Council to cast a new section in-situ.

Patch repair plates welded onto the sheet pile toe in order to reduce the likelihood of undermining of the sea wall.

 

2013

2012

2011                    General Maintenance and repair

2010

2009

 

2008

Filling hole in Greensward, installing horizontal baffle planks, plug gap between concrete and planking. (This was major work funded and carried out by Arun District, with a contribution from MOSA)

 

 

 

 

 

 

 

 

 

 

 

 

 

2007

Exploratory works leading to excavation and re-planking of breastwork and installation of four new anchor piles and associated tie rods.

 

2006

General repair and maintenance.

 

2005

Removal of potential hazards in the face of the main wall (steel reinforcement protruding and exposed edges of steel sheet piling).

 

2004

General repair and maintenance.

 

2003

Repairs to the timber breastwork.

 

2002

Excavated the outfall at Sea Lane and installed rock armour around it. Additional emergency works were carried out following the installation changing the rock face profile. Funded by Arun District Council and the Environment Agency.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2001

A rock toe was added in front of the final piece of breastwork completing the defence.

 

2000

A rock toe was added to the breastwork in to enhance the level of protection the defences offered.

 

1999

General repair and maintenance.

 

1998

General repair and maintenance.

 

1997

43 – Step repairs at Middleton Point at groynes 156, 157,158 and 158a

MARCH 08.jpg
SEPTEMBER 2013.jpg
ROCKS WAITING web.jpg
CRANE and  Rock WEB.jpg
CRANE 1 web.jpg
MOSA Logo Triangles.jpg
bottom of page